Schedule & Progress
Project Completion Dates & Key Milestones
February & March 2010
Library
· Ceiling in progress
· Starting of the painting
Housing
· Snag and de snag period, common areas in progress
Other
· Plant Room ready for communication, external work in progress
April 2010
Library
· Flooring
· Snagging
Housing
· Flat certifications
Other
· Brick Slip on the ground level
· Handover period